Huntersville's Town Board voted unanimously to keep a greenway bridge over N.C. 73 near Lindholm Drive, though the bid came in near $10.4 million, about twice the 2023 estimate.

Huntersville will stay in a state project to build a greenway pedestrian bridge over N.C. 73 near Lindholm Drive, even though its cost has roughly doubled. The Town Board voted unanimously Tuesday night to accept the bid for the N.C. Department of Transportation’s project BL-0119.

Bids were opened Tuesday afternoon, a few hours before the meeting. The bid put the bridge at about $10.4 million, Stephen Trott, the town’s director of engineering, told the board. That is roughly twice the estimate from 2023. NCDOT had asked the town to say by Friday, Nov. 20, whether it would go ahead at the prices bid.

The discussion and vote are in the town’s video of the Nov. 17 meeting, starting about 62 minutes in. The item is 11.A in the agenda packet, which gave no cost before the bid.

What it means for you

  • The bridge will carry the greenway over N.C. 73 at McDowell Creek, near Birkdale Village. People on foot or on bikes will no longer have to cross the highway at street level there.
  • Nothing changes on the road yet. Trott said he expects construction of the wider N.C. 73 to start early next year and take four or five years.
  • The town still has to find about $2.5 million more, and possibly over $5 million. That money would come from future budgets.

Who pays for it

Trott laid out the money for the board:

Source Amount
Original project budget, 2023 estimate a little over $5 million
Regional grant through the planning organization, awarded a little over $3 million
Town match, paid to NCDOT in September $2 million
Cost from Tuesday’s bid about $10.4 million
Gap still to fill a little over $5 million

The town has asked the Charlotte Regional Transportation Planning Organization, known as CRTPO, for another $1.3 million. That request went in by the end of October, and the town will hear in the spring.

Trott said Mecklenburg County is also working on an agreement to put about $1.5 million toward the greenway crossing. Parks and Recreation staff told him so, he said.

If both come through, the town would need about $2.5 million more. Trott said the town can keep applying to CRTPO for more money until the project is finished.

Why the board said yes

One commissioner asked what would happen to the money already spent if the town pulled out. Trott said the town had not asked NCDOT that question. But he said he would expect the state to seek repayment of its costs, because it has already designed the bridge and bought right of way from two commercial property owners. “I would expect a significant amount of the money that the town has already put in would not be returned,” he said.

Board members who spoke all backed the bridge. They pointed to busy Birkdale Village and the crowds crossing for events there. The road is getting wider, too: the same bid covers widening N.C. 73 between Catawba Avenue and Northcross Drive, with one more through lane each way. A street-level crossing will remain, but it will cross six or more lanes. One member said the bridge is a key link toward the greenways of Cornelius, about five miles north, and Davidson, about six miles north.

The rest of the meeting

The board also adopted its consent agenda unanimously. That vote accepted the state grant of about $11.26 million to extend Stumptown Road from Aberfeld Road to N.C. 115. It also approved:

  • the town’s request for CRTPO money for Gilead Road, from Wynfield Creek Parkway to McCoy Road
  • a second request to widen N.C. 115 from Harvest Point Drive to N.C. 73
  • a $3,606,950.70 contract with Lamberts Cable Splicing for underground electric work

Our preview of the Nov. 17 meeting has the details of each item.